University of Gothenburg

Information about the construction work

On this page we share information from Akademiska Hus about the construction work in the near future.

Working hours 07:00-23:00
The project has permission to carry out weekend work, but this is only used when necessary.

Planned works during the period

The project is now entering a new phase, as we can finally begin to see real progress. In week 39, the prefabrication work will commence with the installation of pre-cast concrete inner walls. By the end of the year, we expect the entire building to be assembled, and at the beginning of next year, the façade panels will be installed.

Week 47 (17–21 November):

  •  Prefabrication work with the inner panel (medium disturbance level)
  • Demolition of concrete structure connecting to Block E (high disturbance level)
  • Excavation and removal of soil from the courtyard (medium disturbance level)

Week 48 (24–28 November):

  • Prefabrication work with the inner panel (medium disturbance level)
  • Demolition of concrete structure connecting to Block E (high disturbance level)
  • Removal of site huts from the courtyard (medium disturbance level)

 

Estimated degree of disturbance in different parts of the school.

Green = low
Yellow = medium
Red = high

Image
Illustration of disturbances from the construction work in different parts of the School
Photo: Akademiska Hus

 

If you have questions

Questions about ongoing construction work that are affecting your work:

Campus Service Haga, service.handels@gu.se, 031 786 2160

Questions about the project at large:

Emma Deines, Project Manager, Strategic Project Management, University of Gothenburg, emma.deines@gu.se , +46 721-73 32 44

Questions and wishes regarding the communication about the project:

Maria Norrström, Director of Communications, School of Business, Economics and Law, maria.norrstrom@handels.gu.se , 031-783 1247, 0709-226689