University of Gothenburg

Akademiska Hus has contracted Peab to carry out the construction work following the bankruptcy of the previous contractor.

Planned works during the period:

Week 20 (12 – 16 May):

  • Demolition of geo-construction level 2 (disturbance level: low)
  • Concrete works in deep excavations, vaults, and walls
    (disturbance level: medium)
  • Scaffolding modifications (disturbance level: medium)

Week 21 (19 – 23 May):

  • Demolition of geo-construction level 2 (disturbance level: low)
  • Concrete works in deep excavations, vaults, and walls
    (disturbance level: medium)
  • Scaffolding modifications (disturbance level: medium)

Week 22 (26 – 30 May):

  • Demolition of geo-construction level 2 (disturbance level: low)
  • Concrete works in deep excavations, vaults, and walls
    (disturbance level: medium)
  • Scaffolding modifications (disturbance level: medium)

Estimated degree of disturbance in different parts of the school.

Green = low
Yellow = medium
Red = high

Image
Illustration of disturbances from the construction work in different parts of the School
Photo: Akademiska Hus

 

Explanation of technical terms and level of disturbance:

 

Excavation work

Involves excavation and removal of soil and clay (normal machine noise, beating sound when clay is shaken from the scoop).
Medium level of noise

 

 

If you have questions

Questions about ongoing construction work that are affecting your work:

Campus Service Haga, service.handels@gu.se, 031 786 2160

Questions about the project at large:

Emma Deines, Project Manager, Strategic Project Management, University of Gothenburg, emma.deines@gu.se , +46 721-73 32 44

Questions and wishes regarding the communication about the project:

Maria Norrström, Director of Communications, School of Business, Economics and Law, maria.norrstrom@handels.gu.se , 031-783 1247, 0709-226689