Comprehensive risk assessment of groundwater drawdown induced subsidence

Artikel i vetenskaplig tidskrift
Författare Jonas Sundell
Ezra Haaf
Johannes Tornborg
Lars Rosén
Publicerad i Stochastic Environmental Research and Risk Assessment
Volym 33
Nummer/häfte 2
Sidor 427-449
ISSN 1436-3240
Publiceringsår 2019
Publicerad vid Institutionen för geovetenskaper
Sidor 427-449
Språk en
Ämnesord Cost–benefit analysis, Groundwater drawdown, Infrastructure planning, Risk assessment, Subsidence
Ämneskategorier Infrastrukturteknik, Vattenteknik, Geoteknik, Geovetenskap och miljövetenskap

Sammanfattning

© 2019, The Author(s). We present a method for risk assessment of groundwater drawdown induced land subsidence when planning for sub-surface infrastructure. Since groundwater drawdown and related subsidence can occur at large distances from the points of inflow, the large spatial extent often implies heterogeneous geological conditions that cannot be described in complete detail. This calls for estimation of uncertainties in all components of the cause-effect chain with probabilistic methods. In this study, we couple four probabilistic methods into a comprehensive model for economic risk quantification: a geostatistical soil-stratification model, an inverse calibrated groundwater model, an elasto-plastic subsidence model, and a model describing the resulting damages and costs on individual buildings and constructions. Groundwater head measurements, hydraulic tests, statistical analyses of stratification and soil properties and an inventory of buildings are inputs to the models. In the coupled method, different design alternatives for risk reduction measures are evaluated. Integration of probabilities and damage costs result in an economic risk estimate for each alternative. Compared with the risk for a reference alternative, the best prior alternative is identified as the alternative with the highest expected net benefit. The results include spatial probabilistic risk estimates for each alternative where areas with significant risk are distinguished from low-risk areas. The efficiency and usefulness of this modelling approach as a tool for communication to stakeholders, decision support for prioritization of risk reducing measures, and identification of the need for further investigations and monitoring are demonstrated with a case study of a planned railway tunnel in Varberg, Sweden.

Sidansvarig: Webbredaktion|Sidan uppdaterades: 2012-09-11
Dela:

På Göteborgs universitet använder vi kakor (cookies) för att webbplatsen ska fungera på ett bra sätt för dig. Genom att surfa vidare godkänner du att vi använder kakor.  Vad är kakor?

Denna text är utskriven från följande webbsida:
http://www.gu.se/forskning/publikation/?feedbackForm=true&returnAddress=http%3A%2F%2Fwww.gu.se%2Fforskning%2Fpublikation%2F%3FpublicationId%3D279083&recipientName=Webbredaktion&encodedEmail=aW5mb0BndS5zZQ&publicationId=279083
Utskriftsdatum: 2019-09-18